How to use the payment schedule
- Enter the contract amount.
- Enter retainage if your contract has it.
- Add each payment stage with its share of the contract.
- Check that the stages add up to 100%.
How the schedule works
Each stage payment = contract × stage percentage. With retainage, the amount paid = stage payment × (1 − retainage), and the rest is held. The working shows a running total so you can see how much has been paid at each stage.
Worked examples
New home. 100,000 with stages of 10, 20, 30, 20 and 20%: payments of 10,000, 20,000, 30,000, 20,000 and 20,000, totalling 100%.
With 5% retainage. The foundation payment of 20,000 becomes 19,000 paid and 1,000 held. Across the whole contract, 5,000 is held until completion.
How to interpret the results
Compare the schedule with your contract and your cash flow. If you are borrowing, check that your lender’s draw schedule matches the builder’s.
Tips and common mistakes
- Tie payments to inspections or clearly defined milestones.
- Avoid large up-front deposits; many places regulate them.
- Keep records of each invoice and payment.
- Plan for variations, which change the contract sum.
- Match your lender’s schedule if a construction loan funds the payments, so money is available when each stage is due.
Common stage names
Payment stages are usually tied to visible progress. Typical stages for a new house are a deposit, base or slab, frame, lock-up (roof, external walls, windows and doors), fixing (internal linings, cabinets and fittings) and practical completion. For renovations, stages often follow trades: demolition, rough-in, closing up and finishes. Whatever names you use, define each stage clearly in the contract so everyone agrees when it is complete.
Keeping track
As each stage is invoiced, check the work against the description, keep copies of the invoice and receipt, and record any variations. A simple record makes it easy to reconcile the final account at the end of the job.
Related calculators
Use the contractor quote comparison to choose a builder, the renovation cost calculator for your overall budget and contingency, and the project materials list to track materials you are supplying yourself.
Assumptions and limitations
The tool works with percentages of a fixed contract sum. Variations and cost-plus contracts need separate tracking.